Monday, 3 December 2012

Handover Site Visit 30.11.12


Overview of completed pitch from Prep School


Bodpave surface complete, macadam surface complete- both awaiting car park markings
Bodpave may require redressing/ reseeding in Spring

Bases to be completed to handrails

Ditto

Pitch requires levelling, destoning and seeding in spring

AWP surface and fencing complete

Goals delivered and installed on pitch

Hinge to be refitted to shed door

Sockets required to all bolts

trimming/ treatment required to kickboard/ fence panels

Remaining materials to be removed from site

removable fence panel to be fitted over manhole

Soil vent termination now complete

Thursday, 22 November 2012

Site Visit 21.11.12

Bodpave waterlogged. to be graded/ leveled

Ditto

Goals etc. delivery underway

Kerb between tarmac and bodpave surfaces

Crib wall to be wrapped in chicken wire for additional security- school to carry out post contract

SVP works to be completed to grounds maintenance yard rear

Bund possibly required to Prep car park.
Soft landscape area to be destoned/ seeded in Spring.

Path works to be reviewed in Spring by School/ CVA post contract

Hedge to be removed post contract. CVA to review with client






















Thursday, 1 November 2012

Site Visit 31.10.12

 Setting out of kerbs underway to Middleton Hall Lane

 Shed installed to pitch storage area

 Sand bin complete

kerb to be extended in line with double gate access to pitch to allow smooth transition for bodpave

  Kerb/ bodpave installed adjacent trees

 Majority of carpet now laid with exception of perimeter

 Perimeter carpet to follow

 Adhesive applied to seams in carpet

 Area to rear of maintenance compound- surface compacted

 Dropped kerb and ramp complete to access container

Side store to maintenance compound- surface complete

Tuesday, 23 October 2012

Site Visit 22.10.12

 Macadam strip replaced 20.10.12

 
 Fencing to grounds maintenance compound nearing completion

 Turf pitch waterlogged- levelling to be postponed until dryer weather/ seeding destoning to take place in spring
 Ditto

 Steps to prep school area complete. MST still to forward details for comment

 Area adjacent steps to be graded

 Timber crib wall- awaiting guarding above

 AWP fence posts now installed. Panels to follow shockpad./ carpet installation

 Crib wall/ steps

 Macadam removed where level over kerb

 Car park setting out adjusted- MST to mark up drawing to describe loss of bays



Friday, 12 October 2012

Site Visit 11.10.12

Timber fence installation underway

Macadam still impervious- water sitting

Container base complete/ fencing to enclosure underway

Floodlighting mast installation complete

Overview

Kerbing to rear of compound

Fencing complete to side of compound

Ditto

Manhole to AWP side store

Kerb for sand bin underway