Overview of completed pitch from Prep School
Bodpave surface complete, macadam surface complete- both awaiting car park markings
Bodpave may require redressing/ reseeding in Spring
Bases to be completed to handrails
Ditto
Pitch requires levelling, destoning and seeding in spring
AWP surface and fencing complete
Goals delivered and installed on pitch
Hinge to be refitted to shed door
Sockets required to all bolts
trimming/ treatment required to kickboard/ fence panels
Remaining materials to be removed from site
removable fence panel to be fitted over manhole
Soil vent termination now complete
Monday, 3 December 2012
Thursday, 22 November 2012
Site Visit 21.11.12
Bodpave waterlogged. to be graded/ leveled
Ditto
Goals etc. delivery underway
Kerb between tarmac and bodpave surfaces
Crib wall to be wrapped in chicken wire for additional security- school to carry out post contract
SVP works to be completed to grounds maintenance yard rear
Bund possibly required to Prep car park.
Soft landscape area to be destoned/ seeded in Spring.
Path works to be reviewed in Spring by School/ CVA post contract
Hedge to be removed post contract. CVA to review with client
Ditto
Goals etc. delivery underway
Kerb between tarmac and bodpave surfaces
Crib wall to be wrapped in chicken wire for additional security- school to carry out post contract
SVP works to be completed to grounds maintenance yard rear
Bund possibly required to Prep car park.
Soft landscape area to be destoned/ seeded in Spring.
Path works to be reviewed in Spring by School/ CVA post contract
Hedge to be removed post contract. CVA to review with client
Thursday, 1 November 2012
Site Visit 31.10.12
Setting out of kerbs underway to Middleton Hall Lane
Shed installed to pitch storage area
Sand bin complete
kerb to be extended in line with double gate access to pitch to allow smooth transition for bodpave
Kerb/ bodpave installed adjacent trees
Majority of carpet now laid with exception of perimeter
Perimeter carpet to follow
Adhesive applied to seams in carpet
Area to rear of maintenance compound- surface compacted
Dropped kerb and ramp complete to access container
Side store to maintenance compound- surface complete
Shed installed to pitch storage area
Sand bin complete
kerb to be extended in line with double gate access to pitch to allow smooth transition for bodpave
Kerb/ bodpave installed adjacent trees
Majority of carpet now laid with exception of perimeter
Perimeter carpet to follow
Adhesive applied to seams in carpet
Area to rear of maintenance compound- surface compacted
Dropped kerb and ramp complete to access container
Side store to maintenance compound- surface complete
Tuesday, 23 October 2012
Site Visit 22.10.12
Macadam strip replaced 20.10.12
Turf pitch waterlogged- levelling to be postponed until dryer weather/ seeding destoning to take place in spring
Ditto
Steps to prep school area complete. MST still to forward details for comment
Area adjacent steps to be graded
Timber crib wall- awaiting guarding above
AWP fence posts now installed. Panels to follow shockpad./ carpet installation
Crib wall/ steps
Macadam removed where level over kerb
Car park setting out adjusted- MST to mark up drawing to describe loss of bays
Friday, 12 October 2012
Site Visit 11.10.12
Timber fence installation underway
Macadam still impervious- water sitting
Container base complete/ fencing to enclosure underway
Floodlighting mast installation complete
Overview
Kerbing to rear of compound
Fencing complete to side of compound
Ditto
Manhole to AWP side store
Kerb for sand bin underway
Macadam still impervious- water sitting
Container base complete/ fencing to enclosure underway
Floodlighting mast installation complete
Overview
Kerbing to rear of compound
Fencing complete to side of compound
Ditto
Manhole to AWP side store
Kerb for sand bin underway