Tuesday, 23 October 2012

Site Visit 22.10.12

 Macadam strip replaced 20.10.12

 
 Fencing to grounds maintenance compound nearing completion

 Turf pitch waterlogged- levelling to be postponed until dryer weather/ seeding destoning to take place in spring
 Ditto

 Steps to prep school area complete. MST still to forward details for comment

 Area adjacent steps to be graded

 Timber crib wall- awaiting guarding above

 AWP fence posts now installed. Panels to follow shockpad./ carpet installation

 Crib wall/ steps

 Macadam removed where level over kerb

 Car park setting out adjusted- MST to mark up drawing to describe loss of bays



Friday, 12 October 2012

Site Visit 11.10.12

Timber fence installation underway

Macadam still impervious- water sitting

Container base complete/ fencing to enclosure underway

Floodlighting mast installation complete

Overview

Kerbing to rear of compound

Fencing complete to side of compound

Ditto

Manhole to AWP side store

Kerb for sand bin underway

Thursday, 4 October 2012

Site Visit 03.10.12

Water sitting on impervious strip of macadam

 ditto

 ditto

 ditto

 
Variation in build up of macadam surface- extent is full width of strip laid and 1/2 width of pitch.

 Visible differentiaon in build up, binder content- and also porosity performance

 Floodlighting in progress- mast bases installed

 Overview to back of maintenance yard

 Upper mast components on site in location

 Crib walling complete

Crib wall/ lighting adjacent prep school

Sand bin base- incorrect location- concrete base can be maintained

Lighting masts underway

Sand bin base location incorrect