Overview of completed pitch from Prep School
Bodpave surface complete, macadam surface complete- both awaiting car park markings
Bodpave may require redressing/ reseeding in Spring
Bases to be completed to handrails
Ditto
Pitch requires levelling, destoning and seeding in spring
AWP surface and fencing complete
Goals delivered and installed on pitch
Hinge to be refitted to shed door
Sockets required to all bolts
trimming/ treatment required to kickboard/ fence panels
Remaining materials to be removed from site
removable fence panel to be fitted over manhole
Soil vent termination now complete