Drain overfilling to Grasscrete parking area
Ditto
Areas adjacent path to be destoned/ levelled/ made good
Ditto
Ditto- areas now waterlogged
Grass pitch now reseeded- seed has taken and improved
Ditto
Ditto
Area to rear of compound- to be levelled/ reseeded
Ditto
Brentwood School AWP
ALL WEATHER PITCH
Thursday, 17 October 2013
Wednesday, 26 June 2013
Site visit 24.06.13
Bodpave area now green- but car park markings have not yet been fitted - ACTION MCARDLE
Ditto
Door to shed still fitted poorly
Soft landscape works complete
Additional drainage completed
Some minor stone removal incomplete adjacent steps- to be addressed- ACTION MCARDLE
Soft landscape to perimeter of pitch completed
Grass pitch area complete- requires client supply fence
Monday, 3 December 2012
Handover Site Visit 30.11.12
Overview of completed pitch from Prep School
Bodpave surface complete, macadam surface complete- both awaiting car park markings
Bodpave may require redressing/ reseeding in Spring
Bases to be completed to handrails
Ditto
Pitch requires levelling, destoning and seeding in spring
AWP surface and fencing complete
Goals delivered and installed on pitch
Hinge to be refitted to shed door
Sockets required to all bolts
trimming/ treatment required to kickboard/ fence panels
Remaining materials to be removed from site
removable fence panel to be fitted over manhole
Soil vent termination now complete
Bodpave surface complete, macadam surface complete- both awaiting car park markings
Bodpave may require redressing/ reseeding in Spring
Bases to be completed to handrails
Ditto
Pitch requires levelling, destoning and seeding in spring
AWP surface and fencing complete
Goals delivered and installed on pitch
Hinge to be refitted to shed door
Sockets required to all bolts
trimming/ treatment required to kickboard/ fence panels
Remaining materials to be removed from site
removable fence panel to be fitted over manhole
Soil vent termination now complete
Thursday, 22 November 2012
Site Visit 21.11.12
Bodpave waterlogged. to be graded/ leveled
Ditto
Goals etc. delivery underway
Kerb between tarmac and bodpave surfaces
Crib wall to be wrapped in chicken wire for additional security- school to carry out post contract
SVP works to be completed to grounds maintenance yard rear
Bund possibly required to Prep car park.
Soft landscape area to be destoned/ seeded in Spring.
Path works to be reviewed in Spring by School/ CVA post contract
Hedge to be removed post contract. CVA to review with client
Ditto
Goals etc. delivery underway
Kerb between tarmac and bodpave surfaces
Crib wall to be wrapped in chicken wire for additional security- school to carry out post contract
SVP works to be completed to grounds maintenance yard rear
Bund possibly required to Prep car park.
Soft landscape area to be destoned/ seeded in Spring.
Path works to be reviewed in Spring by School/ CVA post contract
Hedge to be removed post contract. CVA to review with client
Thursday, 1 November 2012
Site Visit 31.10.12
Setting out of kerbs underway to Middleton Hall Lane
Shed installed to pitch storage area
Sand bin complete
kerb to be extended in line with double gate access to pitch to allow smooth transition for bodpave
Kerb/ bodpave installed adjacent trees
Majority of carpet now laid with exception of perimeter
Perimeter carpet to follow
Adhesive applied to seams in carpet
Area to rear of maintenance compound- surface compacted
Dropped kerb and ramp complete to access container
Side store to maintenance compound- surface complete
Shed installed to pitch storage area
Sand bin complete
kerb to be extended in line with double gate access to pitch to allow smooth transition for bodpave
Kerb/ bodpave installed adjacent trees
Majority of carpet now laid with exception of perimeter
Perimeter carpet to follow
Adhesive applied to seams in carpet
Area to rear of maintenance compound- surface compacted
Dropped kerb and ramp complete to access container
Side store to maintenance compound- surface complete