Thursday, 17 October 2013

Site Visit 17.10.13

Drain overfilling to Grasscrete parking area

Ditto

Areas adjacent path to be destoned/ levelled/ made good

Ditto

Ditto- areas now waterlogged

Grass pitch now reseeded- seed has taken and improved

Ditto

Ditto

Area to rear of compound- to be levelled/ reseeded

Ditto

Wednesday, 26 June 2013

Site visit 24.06.13


Bodpave area now green- but car park markings have not yet been fitted - ACTION MCARDLE

 Ditto

 Door to shed still fitted poorly

 Hinge to be replaced to shed- to be addressed- ACTION MCARDLE

 Soft landscape works complete

 Additional drainage completed

 Some minor stone removal incomplete adjacent steps- to be addressed- ACTION MCARDLE

 Soft landscape to perimeter of pitch completed

 Grass pitch area complete- requires client supply fence






Monday, 3 December 2012

Handover Site Visit 30.11.12


Overview of completed pitch from Prep School


Bodpave surface complete, macadam surface complete- both awaiting car park markings
Bodpave may require redressing/ reseeding in Spring

Bases to be completed to handrails

Ditto

Pitch requires levelling, destoning and seeding in spring

AWP surface and fencing complete

Goals delivered and installed on pitch

Hinge to be refitted to shed door

Sockets required to all bolts

trimming/ treatment required to kickboard/ fence panels

Remaining materials to be removed from site

removable fence panel to be fitted over manhole

Soil vent termination now complete

Thursday, 22 November 2012

Site Visit 21.11.12

Bodpave waterlogged. to be graded/ leveled

Ditto

Goals etc. delivery underway

Kerb between tarmac and bodpave surfaces

Crib wall to be wrapped in chicken wire for additional security- school to carry out post contract

SVP works to be completed to grounds maintenance yard rear

Bund possibly required to Prep car park.
Soft landscape area to be destoned/ seeded in Spring.

Path works to be reviewed in Spring by School/ CVA post contract

Hedge to be removed post contract. CVA to review with client






















Thursday, 1 November 2012

Site Visit 31.10.12

 Setting out of kerbs underway to Middleton Hall Lane

 Shed installed to pitch storage area

 Sand bin complete

kerb to be extended in line with double gate access to pitch to allow smooth transition for bodpave

  Kerb/ bodpave installed adjacent trees

 Majority of carpet now laid with exception of perimeter

 Perimeter carpet to follow

 Adhesive applied to seams in carpet

 Area to rear of maintenance compound- surface compacted

 Dropped kerb and ramp complete to access container

Side store to maintenance compound- surface complete