Handover Site Visit 30.11.12


Overview of completed pitch from Prep School


Bodpave surface complete, macadam surface complete- both awaiting car park markings
Bodpave may require redressing/ reseeding in Spring

Bases to be completed to handrails

Ditto

Pitch requires levelling, destoning and seeding in spring

AWP surface and fencing complete

Goals delivered and installed on pitch

Hinge to be refitted to shed door

Sockets required to all bolts

trimming/ treatment required to kickboard/ fence panels

Remaining materials to be removed from site

removable fence panel to be fitted over manhole

Soil vent termination now complete