Thursday, 22 November 2012

Site Visit 21.11.12

Bodpave waterlogged. to be graded/ leveled

Ditto

Goals etc. delivery underway

Kerb between tarmac and bodpave surfaces

Crib wall to be wrapped in chicken wire for additional security- school to carry out post contract

SVP works to be completed to grounds maintenance yard rear

Bund possibly required to Prep car park.
Soft landscape area to be destoned/ seeded in Spring.

Path works to be reviewed in Spring by School/ CVA post contract

Hedge to be removed post contract. CVA to review with client






















Thursday, 1 November 2012

Site Visit 31.10.12

 Setting out of kerbs underway to Middleton Hall Lane

 Shed installed to pitch storage area

 Sand bin complete

kerb to be extended in line with double gate access to pitch to allow smooth transition for bodpave

  Kerb/ bodpave installed adjacent trees

 Majority of carpet now laid with exception of perimeter

 Perimeter carpet to follow

 Adhesive applied to seams in carpet

 Area to rear of maintenance compound- surface compacted

 Dropped kerb and ramp complete to access container

Side store to maintenance compound- surface complete