Kerbs to shed enclosure installed
Macadam surface complete to AWP
Macadam surface to road to be completed later within programme
Wednesday, 26 September 2012
Monday, 24 September 2012
Site Visit 20.09.12
Macadam pitch base installation underway
Kerbs installed- awaiting additional costs/ allowances from McArdle
Floodlighting bases installed
Macadam pitch base
Ditto
Kerbs installed- awaiting additional costs/ allowances from McArdle
Floodlighting bases installed
Macadam pitch base
Ditto
Friday, 14 September 2012
Site Visit 13.09.12

Grounds maintenance forecourt- sub base laid

kerbs to pitch completed

Soil levelling to be completed as levels on CVA drawings- and reviewed at next site visit

Excavation for floodlighting

Soil levelling underway

Septic tank installed
Wednesday, 5 September 2012
Site Visit 03.09.12

Infill adjacent woodland complete, trees and fence removed by school.

Pitch drainage + diversions

rainwater/ levels/ DPC to be reviewed on site at next site meeting where landscape adjacent to grounds dept.

Ditto- discrepancy between section levels and those on site. Resolve treatement on site at next site meeting

Existing septic tank to be emptied and back filled

Extended kerb installed- MST to forward costs

Kerb adjacent grounds dept

Pitch perimeter kerb installation nears completion