Wednesday, 26 September 2012

Site Visit 25.09.12

Kerbs to shed enclosure installed

Macadam surface complete to AWP



Macadam surface to road to be completed later within programme


Monday, 24 September 2012

Site Visit 20.09.12

 Macadam pitch base installation underway
 Kerbs installed- awaiting additional costs/ allowances from McArdle

 Floodlighting bases installed

 Macadam pitch base

Ditto

Friday, 14 September 2012

Site Visit 13.09.12


Grounds maintenance forecourt- sub base laid


kerbs to pitch completed


Soil levelling to be completed as levels on CVA drawings- and reviewed at next site visit


Excavation for floodlighting


Soil levelling underway


Septic tank installed

Wednesday, 5 September 2012

Site Visit 03.09.12


Infill adjacent woodland complete, trees and fence removed by school.


Pitch drainage + diversions


rainwater/ levels/ DPC to be reviewed on site at next site meeting where landscape adjacent to grounds dept.


Ditto- discrepancy between section levels and those on site. Resolve treatement on site at next site meeting


Existing septic tank to be emptied and back filled



Extended kerb installed- MST to forward costs


Kerb adjacent grounds dept


Pitch perimeter kerb installation nears completion